Dear Chandra,

  • This task is created for Business & Technical approval request to the below mentioned project **

Project : QC Process fine tuning

1)V2 Download option.
2)FTR SMS to RO.
3)POST QC Notification to BM .
4)MIS Report - Updates.


Files

Actions #1

Updated by Chandramohan over 5 years ago

  • Assignee changed from Chandramohan to Payodhi

Dear Payodhi,

*This task is created for Technical approval request to the above mentioned project *

Actions #2

Updated by Payodhi over 5 years ago

  • Status changed from New to Approved
  • Assignee changed from Payodhi to Chandramohan

Dear Chandra,

Approved.Pls proceed.

Actions #3

Updated by Chandramohan over 5 years ago

  • Assignee changed from Chandramohan to Vijayakumar

Dear Vijayakumar,

Approved.Pls proceed.

Actions #4

Updated by Vijayakumar over 5 years ago

  • Status changed from Approved to In Progress
  • Assignee changed from Vijayakumar to Shiva_CIMS

Dear Shiva,

  • This task is created for Development team **

Pls find the above description for updation required for DCB.

Actions #5

Updated by Shiva_CIMS over 5 years ago

  • Assignee changed from Shiva_CIMS to Karthik_CIMS

Dear Karthik,

  • This task is created for Testing unit **

Pls check in UAT server and confirm the working status.

Actions #6

Updated by Karthik_CIMS over 5 years ago

  • Assignee changed from Karthik_CIMS to Shiva_CIMS

Dear sir,

Cross checked the UAT testing and confirmed everything is working fine.

Actions #7

Updated by Shiva_CIMS over 5 years ago

  • Assignee changed from Shiva_CIMS to Vijayakumar

Greetings,

The requested Remarks were Replaced in the PostQC Loan Document remark sections in UAT server.
Portal : uat.nocpl.in

Kindly check and confirm

Actions #8

Updated by Vijayakumar over 5 years ago

  • Assignee changed from Vijayakumar to Shiva_CIMS

Dear Shiva,

  • This task is created for production **

We have tested in UAT Link and its working fine. Kindly move to Live server.

Actions #9

Updated by Shiva_CIMS over 5 years ago

  • Assignee changed from Shiva_CIMS to Vijayakumar

Greetings,

The requested Remarks were Replaced in the PostQC Loan Document remark sections.

Also all the requested updates listed below were completed and the same was in live.

1. IMPS -V2 Download option.
2. MIS -Post QC -Pending/ Resolved/ not uploaded status shall be included
3. Dropdown of remarks shall be having prefix of doc name.
4. SMS to BM on FTR, Query, approved cases

Actions #11

Updated by Vijayakumar over 5 years ago

  • Assignee changed from Vijayakumar to Chandramohan

Dear Chandramohan/Payodhi,

For your information,

Our new project was working fine confirmed with our respective OPS Head.

Actions #12

Updated by Vijayakumar over 5 years ago

  • File TC_CB Criteria Updation _ KMB.xlsx added
  • Status changed from In Progress to Closed
Actions #13

Updated by Vijayakumar over 5 years ago

  • File deleted (TC_CB Criteria Updation _ KMB.xlsx)